Date & Time Operations Last updated: 2026-08-20

How to Calculate Business Days in Excel (Excluding Weekends & Holidays)

Calculate project turnaround times, SLA deadlines, and working days using NETWORKDAYS.INTL and WORKDAY.INTL in spreadsheets.

Quick Answer & Formula
Excel Sheets Beginner
=NETWORKDAYS.INTL(start_date, end_date, 1, holidays_range)

To calculate working days between two dates excluding weekends and US holidays: =NETWORKDAYS.INTL(StartDate, EndDate, 1, Holidays_Range). To add 10 business days to a start date: =WORKDAY.INTL(StartDate, 10, 1, Holidays_Range).

How to Calculate Business Days in Excel (Excluding Weekends & Holidays)

Measuring Turnaround Time (TAT), Customer SLA Compliance, and Sprint Milestones requires counting only legitimate business working days.


1. Calculating Elapsed Working Days

=NETWORKDAYS.INTL(A2, B2, 1, $H$2:$H$12)
ParameterCellExample ValueDescription
Project KickoffA209/01/2026Start Date
Project DeliveryB209/30/2026End Date
US Labor Day HolidayH209/07/2026Holiday exclusion
Working Days ResultC221 daysSkips 8 weekend days + 1 holiday

2. Calculating a Future Due Date (Add N Business Days)

To find the exact deadline 15 business days from today:

=WORKDAY.INTL(TODAY(), 15, 1, $H$2:$H$12)

(Format the result cell as Short Date)

?

Frequently Asked Questions

How do I calculate business days for a 4-day or 6-day workweek?

Change the weekend argument in NETWORKDAYS.INTL (e.g. 11 for Sunday-only weekend, or "0000111" for custom work schedules).